Tuesday 5 August 2008

US Network Upgrades

We will be performing a network upgrade on Aug 10th, 2008
starting at 02:00.

There will be a few brief interruptions as trunks are
established, routes are changed, and fail-over is tested. There will
also be one longer interruption (10 to 15 minutes) as servers are moved
to new VLANs.

We expect to be done by 05:00 PDT, with an additional last hour of the
window for testing, troubleshooting and rollback if necessary.

Window Start: Sunday 8/10/08 02:00 US/Pacific (GMT -7)
Window End: Sunday 8/10/08 06:00 US/Pacific (GMT -7)
Duration: Each customer may notice a few short interruptions, and one
longer interruption. Total impact for any one server should be less than
15min. But may be as long as 30 minutes.

No comments: